Iron mines and mining--Iron County (Utah); Mining machinery; Utah International, Inc.
Final Short Line Pit, photo showing completed Utah Construction stripping program there. A total of 6,511,698 cu. yds. of overburden were removed and 3,579 tons of iron ore shipped.
Iron mines and mining--Iron County (Utah); Utah International, Inc.
Armstrong Pit, Lindsay Hill arial. SHE-22, working in area on the 6025 elevation. During three month period, Jan.1 to April 1, 4816 cu. yds of stripping were removed from pit and 15,659 tons of ore were hauled to plant.
Iron mines and mining--Iron County (Utah); Utah International, Inc.
Armstrong Pit, Lindsey Hill, Iron Springs. View of Armstrong Pit on 5989 elevation. During December, 6,869 tons of ore were hauled to plant. No stripping was done in pit.
Iron mines and mining--Iron County (Utah); Mining machinery; Utah International, Inc.
Armstrong Pit, SHD-43, working contract ore on elevation 6005. During month of July, 3,664 cu. yds. of stripping were moved and 8,492 tons of ore were hauled to plant.
Iron mines and mining--Iron County (Utah); Utah International, Inc.
Lindsay Hill - Iron Springs - Armstrong Pit.
Very little mining has been done in Armstrong Pit. During three month period, Oct.1 to Jan.1, 2117 ton of ore were hauled to plant and 3,463 cu. yds. of waste were hauled from pit.